Four ADU Studies in Boston, Melrose, and Waltham: A Small ADU Is Not a Cheap ADU

This week we completed four ADU feasibility studies: two in Boston, one in Melrose, and one in Waltham. The two smallest units, both studios, carry budgets as high as or higher than a one-bedroom of about 700 square feet. The fixed parts of a dwelling cost about the same at any size.

The week in numbers

  • 4 studies in 3 communities: Boston (2), Melrose, and Waltham

  • 2 basement conversions, 1 attached addition, and 1 new detached unit above a new two-bay garage

  • Unit sizes from about 360 to 720 square feet: two studios and two one-bedrooms

  • All-in budgets from $170,000 to $350,000, or roughly $239 to $945 per square foot

  • Feasibility ratings of 2, 6, 7, and 7 out of 10

  • Projected rents from $1,600 to $3,000 a month

What we learned

A small ADU is not a cheap ADU. The basement one-bedroom in Boston, at about 700 square feet, prices at roughly $239 to $325 per square foot. The new studio in Melrose, at just under 500, prices at roughly $350 to $455. The 360 square foot basement studio in Boston prices at roughly $670 to $945. The Melrose study gives the reason. A kitchen, a bathroom, a foundation, an electrical service upgrade, and a sewer run cost about the same for a unit that size as for 800 square feet.

Two Boston basements, two different answers. Both are owner-occupied single-family homes on the same permit path. The first basement has 8-foot ceilings, a 200-amp electrical service, a main drain already re-routed below the slab, two exterior doors, and full-size windows at grade on the rear. It is rated 7. The second has 6 feet 8 inches at most to the underside of the joists, no exterior door, and the boiler, its chimney, the gas meter, and the electrical panel inside the planned unit. The Massachusetts Residential Code (780 CMR, section R305) requires 6 feet 8 inches in a habitable basement, measured from finished floor to finished ceiling, so the floor would have to be lowered 10 to 14 inches with engineered underpinning. Roughly $105,000 to $150,000 of that budget goes to the dig-out, a new heating system for the house, chimney removal, and a second exit before the unit is framed. It is rated 2.

Boston runs on its own rules. Elsewhere in Massachusetts, state law (M.G.L. c. 40A §3 and 760 CMR 71.00) allows one Protected Use ADU on a building permit: a unit of up to 900 square feet or half the main house's gross floor area, whichever is smaller. That law does not apply in Boston. Under the Boston Zoning Code, the owner-occupant of a one-, two-, or three-family home may add one internal ADU within the existing building footprint, on a building permit from the Inspectional Services Department. No zoning hearing is expected. Condominiums and LLC-owned properties are not eligible, and attached and detached ADUs generally still need Zoning Board relief outside Mattapan. For income-eligible owner-occupants, the City offers a grant of up to $7,500 toward design and permitting and a 0 percent deferred loan of up to $50,000, per program terms updated in October 2026.

Study by study

  • Boston. The owner-occupant of a 19th-century single-family wanted a one-bedroom rental in the basement, about 700 square feet. The study rated it 7 out of 10 at $170,000 to $225,000 all-in, with a projected rent of $2,200 to $2,500 a month. The deciding factors were the ceiling height and the electrical and drain work already in place, with written City sign-off on the two exit doors and the bedroom escape window still to obtain.

  • Boston. The owner-occupant of a 1940s single-family wanted to know whether the unfinished basement could become a studio, about 360 square feet. The study rated it 2 out of 10 at $240,000 to $340,000 all-in, with a projected rent of $1,600 to $1,900 a month. The deciding factors were the low ceiling and the heating plant inside the space.

  • Melrose. The owner of a 1950s ranch wanted living space for family, and the study evaluated a one-story attached studio of just under 500 square feet. It rated the project 6 out of 10 at $175,000 to $225,000 all-in, with a projected rent of $1,900 to $2,300 a month if the unit is ever rented. The deciding factors were the size cap set by a small house, a wet rear yard, and a slab foundation that sends the sewer line 80 to 100 feet around the house.

  • Waltham. The owner of a two-family rental property wanted a one-bedroom unit of about 720 square feet above a new two-bay garage. The study rated it 7 out of 10 at $300,000 to $350,000 all-in, with a projected rent of $2,600 to $3,000 a month. The deciding factors were the cost of a full new building and the need for the City's written agreement on which setback and height standards apply.

Common threads

This week brings our detailed findings record to 55 studies since July.

  • In Boston, the interior is the clear path. Five of the 55 studies are in Boston. All three internal conversions proceed on a building permit, with ratings of 9, 7, and 2. Both detached studies faced Zoning Board of Appeal relief or an unsettled permitting route.

  • Small units split into two groups. At least ten of the 55 studies propose a unit of 500 square feet or less. Where the space was already finished or at full height, budgets start at or below $100,000. Where a small unit needs new structure, it carries some of the highest costs per square foot in the record: roughly $580 to $675 for a two-level garage rebuild in Somerville, and $670 to $945 for this week's Boston studio.

  • Half the house can be less than 900. In at least seven of the 55 studies, the "half the house" rule set the ADU limit below 900 square feet. Melrose is the latest.

  • Sprinklers still follow the unit count. On the 29 single-family lots in the record, sprinklers were not anticipated in 20. On the 26 lots with two or more existing units, they were required or likely in 16, awaiting a determination in seven, and not anticipated in three. Waltham is the third, and in all three the ADU is a separate detached building.

  • Two-story backyard units lean on the state rule. At least eight of the 55 studies are two-story detached units in communities whose accessory-building height limit would not allow them. Waltham's limit is one story and 20 feet, and the unit there fits only under the 5-foot accessory-building setbacks, not the district's 15-foot side and 30-foot rear yards. Each study relies on 760 CMR 71.03(3), which bars holding a Protected Use ADU to a stricter dimensional standard than a single-family home, and each recommends getting the building department's position in writing before design.

  • Something to watch: heating equipment in the way. In at least four of the 55 studies, all conversions of basement or ground-level space, the house's heating equipment sits inside the planned unit. Both Boston basements are on that list, and one carries $26,000 to $34,000 to convert the main house to heat pumps.

What this means for your property

  1. Measure the basement before anything else. Record the height to the joists and the lowest pipe, the equipment in the space, and the exterior doors. In Boston, the interior is where to look first.

  2. Do not assume a studio will cost less. Compare cost per square foot and rent at more than one size before you settle on the smallest unit.

  3. If the space is for family, price a standard addition too. The Melrose study notes that an ordinary addition is not held to the ADU size cap and needs no second kitchen, separate metering, or fire separation. It cannot be rented as a separate unit.

Find out what your property can support

A feasibility study answers these questions for your lot: what you can build, what it is likely to cost, what it could rent for, and what to confirm with your city or town first. Your MA ADU is an approved Feasibility Study Provider under the MHP ADU Incentive Program. Request a study at yourmaadu.com.

Figures are preliminary planning ranges drawn from recent feasibility studies. They are not a quote, an appraisal, or legal or financial advice. Property details have been generalized to protect homeowner privacy.